Mitel Forums - The Unofficial Source
Mitel Forums => Mitel MiVoice Business/MCD/3300 => Topic started by: weglik on April 10, 2013, 09:40:53 AM
-
Hi, I couldn' t find the answer anywhere.
We have 2 sites with Mitel 3300 MX
One user will be working 3 days a week at one site, 2 days on the other.
What would be the best solution in my situation.
-
Hot Desking... Look in the help, it is exactly what you are looking for.
-
Depends on your software load. If it is an MX it won't be higher then release 9.
Options are hotdesking ( best )
DSS/BLF key
Ring groups
forwarding
All depends on what is supported on your load.
-
Oops... I missed the MX part of the OPs question. :( LoopyLou is correct again!!!